SunPower and NRG's 250 MW Solar Project Closer to Reality : Greentech Media
包含中國在內的亞洲PV Cell列強, 政府的補助通常集中在上游生產端, 但是美國政府卻在系統端投入重金. US DOE宣布投入 $1.187 billion 金融貸興建250MW的Solar PV Plant, SunPower是這個計畫的stake-holder, 因為此計畫SunPower從此將擺脫只製造Solar Panel的工廠, 進而與First Solar並列為First tier的美國utility scale PV 列強.
全球PV市場冷清清的時候, 讓SunPower VP與我們分享難掩喜悅的一段話:
As SunPower VP Julie Blunden said, "This is the power industry. We're putting in a power station, which two years ago -- the concept did not exist. We are behaving like any power plant developer, trying to provide a thoughtful design and be a good neighbor."
原文中提到的project spec如下:
Size: 250 MW-ac
Acres: 1,935
Acres/MW-ac: 7.7
Total cost: $1,637M ($6.55/W-ac)
Equity: $450M from NRG Energy
Debt: $1,187 from US Federal Financing Bank
Debt as % of total project cost: 73%
Expected break ground date: 2H11
PPA with PG&E for 25 yrs
Tracking: 1-axis (SunPower T0)
EPC: SunPower
O&M: SunPower
包含中國在內的亞洲PV Cell列強, 政府的補助通常集中在上游生產端, 但是美國政府卻在系統端投入重金. US DOE宣布投入 $1.187 billion 金融貸興建250MW的Solar PV Plant, SunPower是這個計畫的stake-holder, 因為此計畫SunPower從此將擺脫只製造Solar Panel的工廠, 進而與First Solar並列為First tier的美國utility scale PV 列強.
全球PV市場冷清清的時候, 讓SunPower VP與我們分享難掩喜悅的一段話:
As SunPower VP Julie Blunden said, "This is the power industry. We're putting in a power station, which two years ago -- the concept did not exist. We are behaving like any power plant developer, trying to provide a thoughtful design and be a good neighbor."
原文中提到的project spec如下:
Size: 250 MW-ac
Acres: 1,935
Acres/MW-ac: 7.7
Total cost: $1,637M ($6.55/W-ac)
Equity: $450M from NRG Energy
Debt: $1,187 from US Federal Financing Bank
Debt as % of total project cost: 73%
Expected break ground date: 2H11
PPA with PG&E for 25 yrs
Tracking: 1-axis (SunPower T0)
EPC: SunPower
O&M: SunPower